Excavation: Our team is responsible for the thorough excavation of the designated site for the Ellington Hotel 3-Residential Building project.
Material Disposal: All excavated materials will be efficiently disposed of, ensuring compliance with Dubai Municipality (DM) regulations.
Logistics: The excavated material will be transported to a DM-approved location using 2XL trucks, each with a capacity of 35 cubic meters per trip.
Key Highlights:
Precision and Safety: Adhering to the highest standards of safety and precision in excavation to prepare the site for subsequent construction activities.
Environmental Compliance: Strict compliance with environmental regulations for material disposal, ensuring minimal environmental impact.
Efficient Logistics: Utilization of high-capacity trucks to streamline the transportation process, reducing the number of trips and optimizing project timelines.
Date
2023-09-08
Client
Al Adrak Contracting
Duration
6 months
Place
Project Location: ELLINGTON HOTEL 3-RESIDENTIAL BUILDING AT DUBAI HILLS ESTATE